Key Projects For Foreign Investment In Guangxi China (2005)  
 Item No. Names of Project & Sponsor Construction Scale & Content Construction Site Construction Conditions Total Invmt ($10000) Mode   Estimated Benefits Preparations finished Connector &Connected Telephone
A. Transportation & Energy Projects
1 A1 Relocation & Expansion Project 135MW Power Plant ( Qinzhou Power Plant, Guangxi) Installed Capacity: 1×135 MW; Long-term plan: 2×135 MW.Carrying out the technical transformation & expansion in the new location,  including powerhouse chimney, cooling tower, equipment foundation, micro-wave office complex and the utility and supporting items such as water supply, environment protection facilities. Economic Development Zone, Qinzhou Port, Qinzhou City Qinzhou Port is located in the coastline transport hub, with the  railway, highway and seaport traffic conditions. It is now provided with a water supply plant with the daily capacity of 55000 tons, which satisfies the demand of the Project. Qinzhou is also provided with perfect com-munications facilities and the construction materials are fully available in the local market. 13785 Joint-venture 0r coopera-tion Internal rate of income: 10%;  profit margin of Investment:    45.15%:      Investment Recovery Period: 5Years Project proposal;             Feasibility study;                 Approval for registration Li Chaogui          Tel: 86-777-2823721          Fax: 86-777-2825840
2 A2 Project Phase III of Qinzhou Port (Qinzhou Port Construction Investment Co. Ltd) Two bulk cargo berths with the capacity of 50000 tons/each with the designed annual throughput: 98×2 ten thousand tons (the hydro- structure of the dock will be designed as per the Class of 100000 tons);One container berth with the annual throughput capacity of  100000 tons. Qinzhou Port, Qinzhou City The power & water supply facilities, the roads, the telecommunication facilities, the living facilities outside the port and the foreign connection institutions have been provided. 9945 Joint-venture , coopera-tion or BOT Internal rate of income: 8.5%;Invest-ment Recovery Period: 11Years Project proposal;             Feasibility study;                 Approval for registration Luo Ming           Tel: 13977796963
3 A3 Pavement&Expan-sion Project for Highway Linking Qinzhou City & Qinzhou Port (Qinzhou Hengyuan Transport Investment Co., Ltd.)  Total length: 27.5km. The alignment is designed as per the standard of Class I highway in the plain with gentle hills. The designed speed is 100km/h. The width of the subgrade: 24.5m, the width of roadway: 2×8m, the hardened road shoulder:2×3.25 m, provided with the 2m-wide median separator. Between Qinzhou City and Qinzhou Port The site is provided with the facilitating traffic conditions and enough land plot. The water, power supply and telecommunication services are guaranteed. 935 Joint-venture , coopera-tion or BOT Internal rate of income: 8.92%; Investment Recovery Period: 13Years Project proposal;             Feasibility study;                 Approval for registration LiangXianhua    Tel: 86-777-2857109           Fax: 86-777-2857102
4 A4 Reconstruction  for Highway from Qinzhou to Xiniujiao (Qinzhou Hengyuan Transport Investment Co., Ltd.)  The length of the existing road is 34 km. with the subgrade width of  12m, the asphalt paved surface width of  6m. The design for the reconstruction is done as per the standard of the highways in the plain with gentle hills. The designed length is  34km; designed speed is 80km/h; subgrade width is 12m, width of the roadway is  2×4.5 m; the hardened shoulder is 2 ×1.5 m.  Qinzhou City The site is provided with the facilitating traffic conditions and enough land plot. The water, power supply and telecommunication services are guaranteed. 360 Joint-venture , coopera-tion or BOT Internal rate of income: 8.92%; Investment Recovery Period: 10Years Project proposal;             Feasibility study;                 Approval for registration LiangXianhua    Tel: 86-777-2857109           Fax: 86-777-2857102
5 A5   Highway from Shajing Avenue to Qinzhou Port(Qinzhou Hengyuan Transport Investment Co., Ltd.)  The highway is a section of Guangxi Binhai Highway Project. The length is  25.3km. The design standard for the highways in the plain with gentle hills is adopted. The designed speed is 80 km/h. The designed subgrade width is 12m; the concrete pavement width is 9 m. It is provided with three bridges with the total length of 740 m.The con-struction items include subgrade, pavement, bridges & culverts, drainage & protection facilities etc.  Qinzhou City The site is provided with the facilitating traffic conditions and enough land plot. The water, power supply and telecommunication services are guaranteed. 2212 Joint-venture or sole-venture Internal rate of income: 8.92%; Investment Recovery Period: 13Years Project proposal;             Feasibility study;                 Approval for registration LiangXianhua    Tel: 86-777-2857109           Fax: 86-777-2857102
6 A6 Highway Project from Dasi of Qinzhou to Xinxu of Jiulong (Qinzhou Hengyuan Transport Investment Co., Ltd.)  Total length: 43km. The design standard for secondary highways in the plain with the gentle hills is adopted. the designed speed is 80km/h. The subgrade width is 12m; the concrete surface width is  9m. The construction items include subgrade, pavement, bridges & culverts, drainage & protection facilities.  Qinzhou City The site is provided with the facilitating traffic conditions and enough land plot. The water, power supply and telecommunication services are guaranteed. 295 Joint-venture or sole-venture Internal rate of income: 8.92%; Investment Recovery Period: 10Years Project proposal;             Feasibility study;                 Approval for registration LiangXianhua    Tel: 86-777-2857109           Fax: 86-777-2857102
7 A7 Construction Project for Qinzhou Section of Guangxi Binhai Highway(Qinzhou Hengyuan Transport Investment Co., Ltd.)  Total length is 48.7km.One section with the length of 34.3km is constructed as per the standard for Class I high-way in the plain with gentle hills.The designed speed is 100 km/h; the designed sub- grade width is 25.5m; the concrete pavement width is 2×7.5m.The other section with the length of 14.4km will be constructed as per the Class II highway in the plain with gentle hills.The designed speed is 80km/h.The sub-grade width is 12m; the concrete pavement width is 9m.The construction items include subgrade, pavement, bridges & culverts, drainage & protection facilities. The starting point is located in Longmen township and the end point is in Dafeng Jiang of Xiniu Township The alignment is arranged along the east coast line of Qinzhou Bay. The terrain is classified into the plain with gentle hills and/or the shallows-tidal-flat area. The geological, hydrological conditions are simple. The project area  enjoys the south subtropical marine climate. The site is provided with abundant road construction materials and satisfactory power & water supply facilities and facilitating traffic conditions.  9690 Joint-venture , coopera-tion or BOT Internal rate of income: 8.92%; Investment Recovery Period: 13Years Project proposal;             Feasibility study;                 Approval for registration LiangXianhua    Tel: 86-777-2857109           Fax: 86-777-2857102
8 A8 South Station of Nanning Road Freight Hub (Guangxi Transport Industry Development Corporation) The annual throughput capacity: 880000 tons; the plot area: 74892 sqm with the total building area of  18685 sqm. Nanning city Provided with the facilitating traffic conditions, the Project site is located in the major industrial zone of Nanning. The water, power and telecommunication lines can be connected from the nearby urban utilities. 665 Joint-venture or coopera-tion   Internal rate of income: 12.65%; Investment Recovery Period: 11.6Years Project proposal;             Feasibility study;                 Approval for registration Zhou Lin        Tel: 86-771-2414328       13878165384
9 A9 Construction of   13#--17# Berths of Fangchenggang (Fangchenggang Port Office) Constructing 5 bulk cargo berths each with 50000 tonnage, the designed annual through-put capacity will be up to  900 ten thousand tons. Fang- chenggang city Fangchenggang Port is enclosed by three-side hills. For the waves are gentle and the silt flushing is balanced, the shelter conditions inside the bay are excellent. In addition, the port will be supported by the existing port. 14398 Joint-venture or coopera-tion   Internal rate of income: 19.76%;  Project proposal;             Feasibility study;                 Ye Shixiang   Tel: 86-770-2892140
10 A10 Construction of the Berth with 20 ten thousand ton-nage and the sup-porting waterway in Fangchenggang Port(Fangchenggang Port Office) The berthing capacity is 0.2 million tons with the annual throughput capacity of 10 million tons. The total length of the dock is 462 m and the width is  21 m. The length of supporting waterway is12km. Fang- chenggang city Fangchenggang Port is enclosed by three-side hills. For the waves are gentle and the silt flushing is balanced, the shelter conditions inside the bay are excellent. In addition, the port will be supported by the existing port. 15758 Joint-venture or coopera-tion   Internal rate of income (taxes unpaid): 9.14%;    Internal rate of income (taxes paid): 7.28% Project proposal;             Feasibility study;                 Ye Shixiang   Tel: 86-770-2892140
11 A11 Project Phase II for Wulin Port ( Investment Promotion Bureau, Pingnan County) The annual throughput is 0.5 million  tons. The main constructed items include warehouses with the building area of  50000 sq.m and other necessary facilities as well as the purchase of the production equipment. Wulin Town, Pingnan county The elevation of Wulin Port is 36m. The land area is the dry farming fields. The site is provided with the long waterfront. The river course is as wide as 1000m,while the normal water depth of the dock is 25m-30m. The civil engineering work has been completed. The existing networks for water, power supply and the telecommu-nication are available now. The port is connected with facilitating traffic conditions. 242 Joint-venture , coopera-tion, sole-venture or others  After the project is put into operation, it will handle 0.5 million tons of transship-ment goods and generate an annual average profit of 380 thousand dollars.   . Project proposal;             Feasibility study;                 Approval for registration        Tentative   design Li Yezhou     Tel: 86-775-7820300        7836898
12 A12 Meicun hydropower Station of Jinxiu County (Guangxi Huineng Rural Electrization Corporation) Installation Capacity:  2×1600 kw. The main construction items include water diversion system, powerhouse, substation and access road etc. Jinxiu county, Laibin city The Power Station is located in the lower reaches of the Hekou Hydropower Station of Jinxiu River, and a station to generate power by the water diverted from the existing Tianchun reservoir. It is 8  km away from Jinxiu County Town. The  access road with 300m-length connects the Class II high-way from Liuzhou to Jinxiu County. 272 Joint-venture or Share participation Annual gen-erated energy:  14.14 million kw·h, which will make an-nual revenue of 444 thou-sand dollars. Inter-nal rate of income: 15.24%, Inter-nal rate of in-come(tax unpaid):10.26% Project proposal;             Feasibility study;                 Approval for registration        Tentative   design Zhang Shijian Tel: 86-771-2185610        13768514196
13 A13 Hujiatian Hydropwer Station(Guangxi Huineng Rural Electrization Corporation)  Installation Capacity:2×1600  kw. The construction items include river dam, diversion system, power house and step-up station. Ziyuan county,  Guilin city Riverside powerhouse is constructed on the exposed bedrock. With sound stability and high hardness, the bed-rock is slightly weathered, relatively integrated, provid-ing an excellent geological condition for the construction of the Project. 158 Joint-venture or Share participation Annual gen-erated energy:  12.16 million kw·h. Internal rate of in-come:12%, Project proposal;             Feasibility study;                 Zhang Shijian Tel: 86-771-2185610        13768514196
14 A14 Sandong Hydropower Station(Guangxi Huineng Rural Electrization Corporation)  Installed Capacity: 2×1250kw. The main construction items include river dam, diversion system, pressure forebay, powerhouse and stem-up station. Gongcheng county, Guilin city The Project site is close to the point for power synchronization. The geological condition is conducive to the construction. 157 Joint-venture or Share participation Annual generated energy is13.04 million kw·h. Internal rate of income is 17.38%. Financial net present value is 593 thous-and dollars (after tax); investment recovery period: 4.4years;  Project proposal;             Feasibility study;                 Zhang Shijian Tel: 86-771-2185610        13768514196
15 A15 Shibashan Hydropower Station, Zhongshan county (Guangxi Huineng Rural Electrization Corporation)  Installed Capacity: 1×630+2×500kw. The main construc-tion items include river dam, diversion system, pressure forebay, powerhouse , stem-up station and living area. Zhongshan county, Hezhou city Construction site is located in Shibashan village, Qing Tang town, 42km far from county seat. 130 Joint-venture or Share participation Annual generated energy is 8.1 million kw·h.Internal rate of income is 11.2%.investment recovery period is 9.5 years. Project proposal;             Feasibility study;                 Approval for registration        Tentative   design Zhang Shijian Tel: 86-771-2185610        13768514196
16 A16 Yulei Hydropower Station of Lipu (Guangxi Huineng Rural Electrization Corporation)Copunty  Installed Capacity:  2520 kw.  The main construction items include river dam, open diversion channel and main powerhouse. Lipu county, Guilin city The Project site is 3 km away from the county seat. 213 Joint-venture or Share participation Annual generated energy is 10.08 million kw·h.Investment recovery period is 9.8 years. Project proposal Zhang Shijian Tel: 86-771-2185610        13768514196
17 A17 Baifu Hydropower station of Leye County (Leye Water Conservancy Development Co., Ltd.) The reservoir is in possession of a total storage capacity of 66.6 million C.M and the regulating storage of 38.86million C.M. The installed capacity is 15MW, with the annual generated energy of 40.13kw·h. The main construction items include river dam, open spillway, water intake, penstock pipeline, power house and step-up station. Xinhua town, Leye county, Baise city The water inflow and the geological conditions meet the demand of the construction of the Project. Baise Leye highway is passing by the site, providing the facilitating traffic. Abun-dant construction materials are available locally. 1870 Joint-venture, cooperation or Share participation Annual generated energy is 40.13 million kw·h;Internal rate of income: 12.6%; investment recovery period:14.7years. Project proposal;             Feasibility study;                 Li Yongqun   Tel: 86-776-7928186        13517566139
18 A18 Tongguwan Hydropower Station of Yulin City (Yulin Heneng Hydropower Co. Ltd) Installed capacity:  3000kw. Construction items: river dam, river course power-house, equipment erection and step-up station etc. Shatian town, Yulin city 141mu of farmland will be submerged.The Project involves no relocation problem. The geological conditions meet the demand of dam construction. The site is provided with the convenient traffic conditions and the construction materials such as sand and rubbles are available locally. 181 Joint-venture or Sole-venture Annual generated energy: 12.97 million kw.h. Inernal rate of income:13.3%. Investment recovery period: 6.82 years. Project proposal;             Feasibility study;                 Approval for registration Yao Yuan     Tel: 86-775-2816010        13707757952
19 A19 Xiakao Water Conservancy Project (undetermined) Installed capacity: 1000kw; the reservoir is regulating annually; construction items: dam, powerhouse and sub-station. Xiakao township, Hechi city Access road is available. 2657 Joint-venture or Sole-venture Annual generated energy: 42.6 million kw·h; annual revenue: 1.2millionUSD    Project proposal;             Feasibility study;                 WeiChengxiu   Tel: 86-778-2293451
20 A20 Jiangnan Hydropower Station of Bobai County(Bobai county Water Conservancy Bureau) Installed capacity: 1600 kw, Construction items include river dam with the length of 180m,   river course type ground powerhouse, step-up station and transmission cable line of 5 km. Bobai town, Bobai county The power demand in the market is high. The construction materials are available locally and the traffic is convenient. 386 Joint-venture, cooperation or Share participation Annual revenue: 217 thousand dollars. Project proposal;             Feasibility study;                 HuangLiming Peng Feilong   Tel: 86-775-8231466
21 A21 Gudi Hydropower Station (Jinchengjiang Water Conservancy Bureau) Installed capacity: 2×1250kw Jinchengjiang District, Hechi city Facilitating traffic conditions; without submerge problems; the length of the special cable line to deliver the power to the grid is short. 157 Joint-venture, coopera-tion or Sole-venture Construction period: 2 years. Upon  completion,annual revenue: 278 thousand dollars.  . Project proposal;             Feasibility study;                 Approval for registration        Tentative   design Wei Jiayong  Tel: 86-778-2584188
22 A22 Nanao Hydropower Station(Jinchengjiang Water Conservancy Bureau) Installed capacity: 2×1250kw Jinchengjiang District, Hechi city Facilitating traffic conditions; without submerge problems; the length of the special cable line to deliver the power to the grid is short. 211 Joint-venture, coopera-tion or Sole-venture Construction period: 1.5 years.Upon  completion,annual revenue: 350 thousand dollars.  . Project proposal;             Feasibility study;                 Approval for registration        Tentative   design Wei Jiayong  Tel: 86-778-2584188